Due to the mentioning of sidewalk disclosures, or rather sidewalk construction, including sketchy illustrations as well as its building in various decisions, the question arises whether the supervision engineer is responsible for its control or if a notification of completion can be issued before the construction of the sidewalk.

The answer is: A notification of completion can be issued before the construction of a prescribed sidewalk. Of course, it would be beneficial for the civil engineer to forward the information of the missing sidewalk to the competent authority. Those responsible include:  relevant experts of MA 37, assisted by MA 28.